Construction Update: Nov. 25, 2015
- Share
- Tweet
- Pin
- Share
Hwy. 42, Sister Bay
Schedule: July 2015 to June 2016
Length: 0.8 miles
Cost: $5.8 million
Location: Village of Sister Bay, Country Walk Drive to Scandia Road
Description: This project involves the reconstruction of Hwys. 42 and 57 in Sister Bay. The work includes traffic and erosion control, signing, storm sewer, sanitary sewer, water main, curb and gutter, sidewalks, lighting, concrete and asphalt pavement, and landscaping.
Nov. 23 to Dec. 31: Crews plan to install the street lights. Anticipated delivery is December 2015 with installation scheduled shortly thereafter. Between January and late May, crews plan to begin work on the remaining sidewalk, landscaping, and asphalt paving items as weather conditions permit with a tentative startup planned for mid to late April 2016.
Traffic Impacts: Between Nov. 20 and spring 2016 construction startup, all roads will be open to traffic during the winter months. For more information, go to: projects.511wi.gov/wis42/.