Sister Bay Construction Update

Hwy. 42 Village of Sister Bay

Schedule: July 2015 to June 2016

Length: 0.8 miles

Cost: $5.8 million

Location: Country Walk Drive to Scandia Road

Description: This project involves the reconstruction of Hwys. 42 and 57 in Sister Bay. The work includes traffic and erosion control, signing, storm sewer, sanitary sewer, water main, curb and gutter, sidewalks, lighting, concrete and asphalt pavement, and landscaping. Crews plan to complete asphalt paving on Hwy. 57 and Gateway Drive, as well as the driveway approaches in that area. The pedestrian path that presently ends at the Church Hill Inn driveway will be extended with temporary asphalt, connecting to the crosswalk at Hwy. 57/42 using a combination of new temporary asphalt and existing paved paths. Crews also plan to work on the gravel shoulders, topsoil placement, and seeding.

Traffic Impacts: This project consists of detours around the staged work areas. Currently, Hwy. 57 is detoured for both northbound and southbound traffic lasting through Sept. 3. The detour is Hwy. 57 to Country Walk Drive to Hwy. 42. Pedestrians are advised to avoid the active construction area around Hwy. 57 and Gateway Drive. For more information, go to projects.511wi.gov/wis42.

Related Organizations