Hwy. 42 Village of Sister Bay

Schedule: July 2015 to June 2016

Length: 0.8 miles

Cost: $5.8 million

Location: Country Walk Drive to Scandia Road

Description: This project involves the reconstruction of Hwy. 42 and Hwy. 57 in Sister Bay. The work includes traffic and erosion control, signing, storm sewer, sanitary sewer, water main, curb and gutter, sidewalks, lighting, concrete and asphalt pavement, and landscaping. Crews planned to pour the new concrete sidewalk along Hwy. 57. They also planned to install the permanent signs along Hwy. 57 and Gateway Drive.

Traffic Impacts: This project consists of detours around the staged work areas. Currently, Hwy. 57 is detoured for both northbound and southbound traffic lasting through Sept. 3. The detour is Hwy. 57 to Country Walk Drive to Hwy. 42. Pedestrians are advised to avoid the active construction area around Hwy. 57 and Gateway Drive. For more information, go to projects.511wi.gov/wis42/.