Ephraim Highway Project Update


Some Ephraim homes will temporarily lose driveway access in the days ahead as crews install curbs along the inland side of the highway.

Some driveways will be impossible for up to two weeks as concrete cures. For those properties with multiple driveway entry points crews will pour curbs one at a time to maintain access. For two businesses crews will pour half of the curb at a time to maintain access.

After curbs are poured, sidewalks will follow. New streetlights within the reconstruction area have been installed, and Administrator Brent Bristol reports that most of the foundations for the other street lights have been poured and will have lights mounted as soon as the concrete cures.