  • Construction Updates, Oct. 9, 2015

    Hwy. 42, Forestville Schedule: Aug. 2015 to Oct. 2015 Length: 0.05 Miles Cost: $475,000 Location: Village of Forestville, between County X and County J Description of project: The project involves removing the existing box culvert and replacing it with a new bridge meeting current design standards for vehicular loading and structure design. Bridge approaches will […]

  • Construction Update, Sept. 25-Oct. 2

    Hwy. 57 Schedule: Sept. 2015 to Nov. 2015 Length: 0.5 Miles Cost: $932,686 Location: Pine Road Mitigation Site and County C and Hwy. 57 intersection. Description of project: The project involves mitigation site maintenance at the Pine Road Mitigation Site and constructing J-turns at the intersection of County C and Hwy. 57. Work includes traffic […]

  • Construction Update, Sept. 18 – 25

      Hwy. 57 and County Road C Schedule: Sept. 2015 to Nov. 2015 Length: 0.5 Miles Cost: $932,686 Location: Pine Road Mitigation Site and County C and Hwy. 57 intersection. Description of project: The project involves mitigation site maintenance at the Pine Road Mitigation Site and constructing J-turns at the intersection of County C and […]

  • Municipal News, Sept. 11: Jacksonport Host Informational Session on Water Quality

    Town of Jacksonport: The Environmental Committee is hosting a public information session on water quality and manure handling at 6 pm on Sept. 14, with Gregory T. Kleinheinz, R.S., Ph.D.,Viessmann Chair of Sustainable Technology, Professor, Environmental Engineering Technology from the University of Wisconsin – Oshkosh; Bill Schuster and Dale Konkol from the Door County Soil […]

  • Construction Update, Sept. 11-18

    Hwy. 57 and County Road C Work will begin Monday, Sept. 14, on a $1.04 million safety improvement at the intersection of Hwy. 57 and County C with the construction of a J-turn intersection. Peters Concrete Company, Green Bay, is the prime contractor. The project involves constructing a J-turn intersection at Hwy. 57 and County […]

  • CONSTRUCTION UPDATE, Sept. 4 – 11

    Hwy. 42 Village of Forestville, between County X and J Schedule: Aug. to Oct. 2015 Length: 0.05 Miles Cost: $475,000 Description of project: The project involves removing the existing box culvert and replacing it with a new bridge meeting current design standards for vehicular loading and structure design. Bridge approaches will be constructed, which include […]